AccessMyLibrary provides FREE access to over 30 million articles from top publications available through your library.
Create a link to this page
Copy and paste this link tag into your Web page or blog:
The "no damage for delay" clause is a common method used by owners and contractors to shift the risks of delay on construction projects to subcontractors--the party with the least amount of control over the progress of construction. As noted in Donald Gregory's article, Negotiating a Contract You Can Live With (The Contractor's Compass, 3rd Quarter 2005, p. 9), the "no damage for delay" clause is considered one of the top 10 "deadliest" provisions in a subcontract and should be avoided.
All is not lost, however, in the event that a subcontract contains such a provision. The subcontractor may still be entitled to additional compensation for delays because there exist several exceptions to the enforcement of the "no damage for delay" clause. In addition, delay-related damages such as impact and disruption damages may also be recoverable.
The key to preserving any potential delay or impact claim is strict compliance with the terms of the subcontract--specifically, the notice requirements.
A Typical "No Damage For Delay" Clause
Typically, a "no damage for delay" provision provides that the only remedy to the subcontractor for delays wit[ be an extension of time. For example:
[Should the Subcontractor's performance be delayed by any acts of the Contractor, its subcontractor or suppliers, or delayed by the acts or causes which entitle Contractor to an extension of time under the prime contract, the Subcontractor shall receive an extension of time for its performance. Subcontractor agrees that an extension of time shall be its sole remedy for delays. Subcontractor shall notify the Contractor in writing within five days of the event giving rise to the delay or the Subcontractor's claim for an extension of time is forever waived.]
Under this provision, the subcontractor receives a time extension for "excusable" delays, which are events "beyond the control" of the parties. It is typical for performance time to be extended in cases of unusually severe weather, natural disasters, acts of government, or unforeseeable Labor strikes. But why should the subcontractor absorb additional costs for delays actually caused by the contractor or its subcontractors, delays which are categorized in the industry as "compensabre"?